Welcome to the official website of Henan Yuke New Material Co., Ltd!

Telephone:15639728585 / 15649298103 / 15037180276  / 15036003371 

WeChat
WeChat

Waterproof backing board

新闻资讯

新闻资讯

current position: Home > News Center > Industry News

contact usContact Us

Henan Yuke New Material Co., Ltd

Phone: 15639728585

Phone: 15649298103

Phone: 15037180276

Phone: 15036003371

Email: 2634107059@qq.com

Website: hnykxcl.cn

Address: No.1 Courtyard, Fulin South Road, Baqian Township, Airport District, Zhengzhou City, Henan Province

How to install waterproof backing board on the wall?

2025-11-24 16:20:06
times

Construction guide for waterproof backing board on the wall


1、 Overview of waterproof backing board


Waterproof backing board is a new type of material widely used in building decoration engineering, mainly used for wall treatment in damp environments such as bathrooms, kitchens, balconies, etc. It is made of waterproof materials such as high-density polyethylene (HDPE) or polyvinyl chloride (PVC), which have excellent waterproof and moisture-proof properties, as well as characteristics such as lightweight, easy cutting, and easy construction.


The main functions of waterproof backing board include:

1. Form an effective waterproof barrier to prevent moisture from penetrating into the interior of the wall

2. Provide a smooth base layer for subsequent decorative materials such as tiles

3. Reduce the problem of mold growth on walls caused by moisture

4. Extend the service life of wall decoration materials


2、 Preparation work before construction


1. Material preparation


-Waterproof backing board: Calculate the required quantity based on the construction area, and it is recommended to prepare an additional 5% as loss

-Special adhesive: choose the adhesive material that matches the backing board

-Waterproof sealant: used for joint treatment

-Fixed components: plastic expansion bolts or stainless steel self tapping screws

-Yin Yang corner strip: used for strengthening treatment of corner parts


2. Tool preparation


-Measuring tools: tape measure, level, ink box

-Cutting tools: art knife, electric cutting machine

-Mixing tool: electric mixer

-Construction tools: toothed scraper, rubber hammer, trowel

-Protective tools: gloves, goggles, masks


3. Grassroots treatment


1. Wall inspection: Ensure that the flatness error of the wall does not exceed 3mm/2m, and there are no defects such as hollowing or cracking

2. Cleaning treatment: Thoroughly remove wall dust, oil stains, release agents, and other substances that affect bonding

3. Moisturizing treatment: For the base layer with high water absorption rate, it should be sprayed with water appropriately before construction to moisten it

4. Defect repair: Use cement mortar to repair holes and cracks, ensuring a solid base layer


3、 Construction steps for waterproof backing board on the wall


1. Bullet line positioning


1. Use a spirit level to mark the horizontal reference line on the wall

2. Based on the size of the backing board, plan the layout scheme and minimize cutting as much as possible

3. Mark the fixed point positions on the wall, with a spacing of generally 300-400mm


2. Adhesive preparation


1. Mix the adhesive with clean water according to the ratio specified in the product manual

2. Use an electric mixer to stir at low speed for 3-5 minutes until uniform and particle free

3. Let it stand and mature for 5 minutes, then stir again before use

4. Note that the adhesive should be used up within the specified time (usually within 2 hours)


3. Pasting of backing board


1. Use a toothed scraper to evenly apply the adhesive to the wall and the back of the backing board

2. The thickness of the adhesive should be controlled within 3-5mm, and the scraping direction should be consistent

3. Stick the backing board onto the wall in the predetermined position and adjust it slightly to the accurate position

4. Gently tap with a rubber hammer to ensure full contact with the wall surface

5. Check the verticality and levelness with a spirit level in a timely manner


4. Mechanical fixation


1. Perform mechanical fixation before the initial setting of the adhesive (about 30 minutes later)

2. Use an electric drill to drill holes at the marked positions, with a depth 5mm longer than the fixed parts

3. Insert the plastic expansion sleeve and fix it with self tapping screws

4. The fixing parts should be slightly lower than the board surface for ease of subsequent processing

5. Fixed point density should be increased at the corners and edges


5. Seam treatment


Leave a 3-5mm gap between the boards to accommodate thermal expansion and contraction

2. Fill the joints with specialized waterproof sealant

3. Use a trowel to compact and smooth the sealant, forming a continuous waterproof layer

4. Prefabricated internal and external corner strips should be used to strengthen the corners


6. Node processing


1. Intersection between wall and floor: The backing board should extend 20mm below the finished surface of the floor

2. Surrounding the pipeline: Use specialized sealant for circular waterproofing treatment

3. Door and window openings: The backing board should be wrapped around the outside of the door and window, and the joint should be strengthened with sealing

4. Pre embedded parts: Make a "cross" cut and seal the surrounding area after installation


4、 Construction precautions


1. Environmental requirements: The construction environment temperature should be between 5-35 ℃ to avoid rainy and snowy weather during construction

2. Material storage: The backing board should be placed flat in a dry place, avoiding direct sunlight and heavy pressure

3. Construction sequence: Follow the principle of "facade first, then plan, far first, then near"

4. Quality control: Inspection and acceptance should be conducted for each completed process

5. Safety measures: Proper protection is required for high-altitude operations, and insulation of electric tools should be checked before use


5、 Common problems and solutions


1. Hollowing problem: caused by uneven application of adhesive or improper treatment of the base layer

-Solution: Remove the hollow areas and reprocess the grassroots level before providing subsidies


2. Joint cracking: caused by improper selection of sealant or non-standard construction

-Solution: Remove the original sealant and choose a product with better elasticity for reprocessing


3. Surface deformation: Improper storage or immediate exposure to high temperatures after construction

-Solution: Choose qualified products and avoid direct sunlight exposure after construction


4. Poor adhesion: expired adhesive or incorrect ratio

-Solution: Strictly follow the instructions to prepare the adhesive, expired products cannot be used


6、 Acceptance criteria


1. Surface flatness: Check with a 2m ruler, deviation ≤ 3mm

2. Seam width: uniform and consistent, controlled within the range of 3-5mm

3. Fixed point spacing: meets design requirements, generally ≤ 400mm

4. Waterproof performance: After construction is completed, a 24-hour closed water test can be conducted

5. Appearance quality: No defects such as hollowing, cracking, or curling edges


7、 Suggestions for subsequent construction


After the completion of the backing plate construction, it should be cured for 24 hours before proceeding to the next process

2. Before tiling, an interface agent should be applied to the surface of the backing board to enhance the bonding strength

3. The installation location of heavy-duty pendants should be reinforced in advance

4. Avoid scratching the waterproof layer with sharp objects during subsequent construction


By following the detailed construction steps and precautions above, the construction quality of the waterproof backing board on the wall can be ensured, providing reliable waterproof protection for the building. During the construction process, every link should be strictly controlled, especially key parts such as base treatment and node waterproofing, in order to fully utilize the performance advantages of waterproof backing boards.